Price revision: what it covers, and what it does not

An index formula adjusts the price of a long contract when costs move. It never returns the whole of the increase: part of the price stays fixed, by construction.

When it applies

Revision is not decided along the way: it has to be provided for by the contract, and generally applies to contracts running longer than a year or where the CPS expressly says so. With no clause there is no revision, whatever increase is observed.

The base index value is the one for the month bids were submitted: that is the point of comparison for every later calculation.

The fixed part, the one that never moves

The usual formulas have a fixed part and a revisable part. In the formula most widespread in building work, the fixed part is 0.15 and the revisable part 0.85, applied to the ratio between the index for the period and the base index.

The direct consequence: even where costs rise sharply, around 15 % of the price will never be revised. Revision cushions, it does not compensate.

The indices

The construction indices are published monthly by the ministry responsible for finance: general building index, structural work, finishing work, civil engineering, wages. The contract names the one that applies, sometimes a weighted combination of several.

Where the index for the month has not been published yet, common practice is to use the latest available index and then put it right. A Moroccan public site, revisiondesprix.ma, offers that calculation and the index base free of charge; what it does not do is connect the result to the payment statement, the retention and the invoice.

What to keep

Revision is often disputed: the supporting documents count as much as the arithmetic.

  • The base index, with the month bids were submitted
  • The index used for each period, and its source
  • The exact formula written into the contract, weightings included
  • The revised amount, period by period, to reconcile with the statements

Revision and actualisation: two different things

The two are often confused. Actualisation corrects the price between the date bids were submitted and the actual start of the works, where that start is late. Revision follows the movement of costs during performance, period by period.

So one contract can undergo an actualisation at the outset and then revisions throughout its performance. Both rest on indices, but they are not calculated at the same moment nor on the same base.

In both cases the result is only worth something if it is attached to a payment statement: a revision worked out on the side, never carried onto a works situation, brings in nothing.