The interim payment statement, line by line

A payment statement is not an invoice: it is a running total since the contract began, from which what has already been paid and what must be withheld are subtracted. The order of operations matters, and that is where mistakes become expensive.

A running total, not a monthly amount

The statement — the décompte, as every document you will be handed calls it — starts from the cumulative total of work performed since the contract began, not from the month just ended. Deductions and withholdings are then applied, and the total of all previous statements is subtracted to arrive at the amount payable on this one.

That mechanism explains much of the discrepancies seen in practice: something left out of an old statement is dragged through every later one, since each of them starts again from the cumulative total.

The order of operations

Common practice runs in this sequence: cumulative work performed, then price revision if the contract provides for it, then retention money, then repayment of the advance, then any late-delivery penalties, and finally VAT on the resulting base.

Changing that order changes the result. Applying retention before revision, for instance, does not produce the same net amount payable.

  • Cumulative work performed since the start
  • Price revision, where the contract provides for it
  • Retention money, up to its cap
  • Repayment of the advance, at the rate set in the contract
  • Any late-delivery penalties
  • Deduction of statements already paid

What has to be attached

A statement sent without an attachement or a signed procès-verbal tends to be turned against the company: that is the document proving the quantity performed. The attachements must cover the period of the statement, and their cumulative total must match the statement’s own.

The date of the signed procès-verbal then becomes the starting point of other calculations: service performed for the payment deadline, acceptance for retention and for penalties. It is worth getting that date right.

The mistakes that come back most often

They are not spectacular ones. They are arithmetic, repeated over twelve months.

  • Retention money withheld beyond its cap, and never put right
  • The advance repaid at a different rate from the one in the contract
  • Revision calculated on the amount including VAT instead of excluding it
  • Penalties counted from the original completion date, when a service order has moved it
  • A statement sent without an attachement, refused, then forgotten

What you can check yourself, in ten minutes

Take your latest statement and ask four questions. Does the cumulative total match the sum of the signed attachements? Has cumulative retention gone past the cap set in the contract? Is the advance being repaid at the rate written in the CPS, rather than by an improvised rule of three? Does the total of previous statements deducted match what you have actually been paid?

If the answer to any one of them is “I do not know”, that is where the gap is. Going back over an old statement is unpleasant, but it is the only way to stop an error that would otherwise carry forward all the way to the final statement.

The final statement, precisely, closes the contract: an error that has survived that long becomes very hard to correct. That is the moment to reconcile, one last time, the cumulative attachements, the cumulative statements and the contract amount including any amendments.